Friday, July 19, 8am-12pm: We will finish clearing temporary access paths to the bridge locations, and begin staging materials. (We are trying a mid-week date for the first time.)
Saturday, July 20, 8am-12pm: We will finish staging if required then move the wood to the bridge locations. If that goes quickly we will start bridge building.
Meet at the RCF parking lot on Conesca Road. You won't need any tools, but please bring work gloves, water, your favorite bug spray, and footwear appropriate for rough terrain.
RAIN DATE: Sunday, July 21, 8am-12pm
We plan on working if it is a little wet, but not if there are heavy rains. If either Friday or Saturday is cancelled, notification will be sent the night before.